B&K are continuing to work hard on site, with each week bringing another extensive list of what has been achieved. The scaffolding surrounding Snowfields Academy has now all come down, unveiling the beautiful brickwork and flagstone making up the exterior of the building. The scaffolding around Bearsted Primary Academy will gradually be coming down this week once the last of the brickwork is complete. The majority of our external doors have been fitted, and classroom walls are all now closed up and ready for painting. The last of the data cabling and fire cabling is being installed alongside radiators, dado trunking for smart boards and ventilation ducting. Our UKPN SubStation has been connected to the electricity grid and all floors are being prepared for covering. Our car park is really taking shape, rapidly showing the large amount of parking available to our staff and parents. We can’t wait for when we are next on site to see the new changes and how both schools are taking shape.